COCA-COLA FACTORY
The construction of the Coca-Cola factory stands as one of Pholabi’s largest and most complex projects.
Our company was responsible for the installation of load-bearing metal structures, sandwich panel cladding and the organization of the water intake system.
The project was carried out for Element Construction under the design-build principle, resulting in the completion of the largest Coca-Cola factory in Transcaucasia within just 9 months.
Large-scale operations were conducted across multiple locations simultaneously, employing more than 150 workers throughout the project.
PROJECT DETAILS
2019 Year
CUSTOMER
“Cola-Cola Bottlers Georgia”
COMPLETED WORK
- Production and installation of load bearing metal constructions;
- Installation of sandwich panels;
- Installation of water intake systems;